Accessibility mode is enabled

Skip to Top / Tab to View Menu Options
Skip to Left Navigation / Tab to View Content

Renovation AND EXPANSION Schedule

While the Memorial Auditorium has construction beginning in Spring of 2018 and the Sacramento Community Center is scheduled to begin in Spring/Summer of 2019, details for the Sacramento Convention Center are tentative. The phasing schedule will adjust and solidify as the project moves forward.

Memorial Auditorium

Construction  Late June 2018
Reopens May 2019 - July 2020
Restoration  August 2020 - November 2020 
Project Completion  November 2020 
   

Community Center Theater

Exterior Construction  January- June 2019
Interior Construction  (Theater Closed) July 2019- September 2020
Reopening September 2020
Remaining Exterior Construction October 2020-March 2021
Project Completion  April 2021 
 

Convention Center

Construction Start December 2018 
Convention Center Closure  Late July 2019
Convention Center Re-Opening November 2020
Project Completion March 2021