PROJECT UPDATES

The City of Sacramento Department of Utilities has been in service for more than 100 years. The department has grown as the city has grown and now serves more than 480,000 customers with a variety of critical services, including water, wastewater and storm drainage. 

Utilities delivers valuable services that aren’t obvious on a day-to-day basis. Beyond water and wastewater, activities include:

  • Regulatory compliance
  • Protecting water rights and quality
  • Responding to sanitary sewer overflows to prevent discharges of sewage to local creeks and rivers
  • Investment for future improvements
  • Maintaining adequate financial reserves to provide financing for long-term capital improvement projects

 

 

WASTEWATER PROGRAM

In Design

Cost (Millions)

% Complete

CWTP MCC L and MCC B Replacement

$0.49

91%

CWTP Water Supply Rehabilitation

$0.16

98%

South Pocket Sewer Rehabilitation Program

$0.18

100%

Sump 137 Reconstruction

$1.64

97%

In Construction

Cost (Millions)

% Complete

9th Street Sewer Replacement L to G St

$4.28

23%

Basin 52 Master Plan Update

$0.04

94%

Power Meter Buyback Program

$0.13

83%

Security Lighting Controls

$0.98

93%

South Pocket I&I Reduction Project

$0.68

18% 

VFD Replacement Program

$0.40

83%

Completed

Cost (Millions)

% Complete

2nd/3rd Ave Sewer Replacement Alhambra to 32nd St

$0.36

100%

3rd Street Relief Sewer Study Update

$0.01

100%

7th Street Sewer Replacement P to K St

$7.70

100%

16th Ave Sewer Replacement Norton Way to 28th St.

$0.18

100%

34th Ave Easement Sewer Rehabilitation, Gilgunn to Ricky Dr

$0.37

100%

35th Ave Parking Lot Seal and Repair

$0.05

100%

38th St between H St. and McKinley Blvd

$0.32

100%

41st/42nd Street Easement Sewer Rehab 2nd to Sherman Way

$0.38

100%

51st/52nd Easement Sewer Replacement 2nd Ave to V St.

$0.31

100%

56th Street, H Street to J Street

$0.70

100%

65th Ave/Benbow St Easement Sewer Replacement

$0.32

100%

Arc Flash Hazard Analysis

$0.23

100%

Basin 85 Influent Sewer Rehabilitation

$0.78

100%

Brently Dr Sewer Replacement, Milner Way to 25th St.

$0.36

100%

CIPP Rehabilitation 2013

$0.48

100%

CIPP Rehabilitation 2014 and 2015

$0.69

100%

CSS Large Facility Flow Meters

$0.22

100%

D Street Sewer Replace. 19th to 20th St

$0.36

100%

D/E Alley Sewer Replace. 13th to 15th St

$0.49

100%

F Street Sewer Replace. 18th to 20th St.

$0.31

100%

Freeport Blvd Sewer Replace. 7th to Bidwell

$0.97

100%

Golfview/Hogan Dr. Easement Sewer Rehabilitation, 50th to 51st Ave

$0.20

100%

Grove Ave Easement Sewer Rehabilitation

$0.14

100%

Harbor Light Way Sewer Replacement - Riverwind to Zephyr

$0.15

100%

J and 33rd Easement Sewer Abandonment

$0.21

100%

L Street Sewer Replace. 19th to 20th St.

$0.39

100%

Lampasas Sewer Replacement - Norwood to Grove

$0.51

100%

Laurie Way Sewer Replacement Project, at Detroit Blvd.

$0.07

100%

Meadowview Site Lighting and Security

$0.21

100%

Misc. Sewer Manhole Rehab

$0.14

100%

O/P Alley Sewer Replace. 17th to 18th

$0.12

100%

Oak Park Regional Storage

$10.26

100%

P Street Sewer Replacement 5th to 7th

$1.31

100%

P/Q Alleys Sewer Replace. 16th to 17th St.

$0.21

100%

Pioneer River Intake Structure

$0.15

100%

Q/R Alley Sewer Replace. 16th to 17th St.

$0.11

100%

R St Sewer Replace. 18th to 20th St

$0.01

100%

R/S Alley Sewer Rep. 3rd to 4th St.

$0.21

100%

R/S Alley Sewer Rep. 27th to 29th St.

$0.28

100%

Sewer Flow Monitoring

$0.26

100%

Sewer Sump Flow Meters

$0.63

100%

Sherman Way Easement Sewer Rehabilitation, Miller Way to 39th St

$0.24

100%

Sump 40 Electrical Rehab

$0.51

100%

Sump 80 Reconstruction

$0.56

100%

Sump 137, Greenhaven Dr. Forcemain Extension

$0.30

100%

Sump 143 Reconstruction

$0.44

100%

Sump 146 Reconstruction

$0.71

100%

Upper Sac South Drainage Canal Sewer - Phase 1,2,3

$0.80

100%

V/W Alley Sewer Replace. 14th to 15th

$0.24

100%

Wastewater Pipe System Condition Assessment

$0.07

100%

Other

Cost (Millions)

% Complete

Basin 52 Master Plan Update

$0.04

94% in Construction

Brick Main Preservation

$0.05

100% Bid/Award

Master Plan Sewer Modeling

$0.05

100%

Misc. Sewer Repairs

$0.20

98% in Design

On-Call Engineering Design Support

$0.07

100%

On-Call Sewer Cleaning/CCTV

$0.02

67%

On-Call Trenchless Sewer Repairs

$0.18

97% in Design