ZA_AGDA.RPT
| ZONING ADMINISTRATOR HEARING |
03/16/2006
| ********************************************************************************************************************************* |
| Please Turn off All Cellular Phones and Pagers Prior to Entering the Hearing Room |
| Order of Hearing Items to be set by the Zoning Administrator |
| ********************************************************************************************************************************* |
| ** |
HEARING ITEMS:
1
(Project Planner: Sandra Yope)
Z050334
File Number:
Site Address:
8500 MORRISON CREEK DR (D6, Area 3)
Location:
SE CORNER FLORIN PERKINS & MORRISN CREEK (D6, Area 3)
Owner:
OK & B, 8615 ELDER CREEK RD #20, SACRAMENTO CA, , 95828
Applicant:
SURVEYOR'S GROUP, INC., 9001 FOOTHILLS BL. SUITE 150, ROSEVILLE, CA, , 95747
Proposal:
| Zoning Administrator Tentative Map to subdivide one parcel into two parcels totaling 1.79+ vacant acres in the |
| Heavy Industrial-S (M-2S) zone. |
Parcel #:
0640020086
2
(Project Planner: Sandra Yope)
Z050326
File Number:
Site Address:
2723 ALTOS AV (D2, Area 4)
2733 ALTOS AV (D2, Area 4)
Location:
2723 & 2733 ALTOS AVE (D2, Area 4)
Owner:
CANDACE NIGG, 2625 CROSBY WAY, SACRAMENTO, CA, , 95815
Applicant:
CANDACE & MARK NIGG, 2625 CROSBY WAY, SACRAMENTO, CA, , 95815
Proposal:
| Zoning Administrator Tentative Map to subdivide two parcels into four parcels totaling 0.60 partially developed |
| acres in the Single Family Residential (R-1). Zoning Administrator Subdivision Modification to create three |
| interior lots less than 52 feet wide (Parcels A, C, and D). Zoning Administrator Subdivision Modification to create |
| one interior lot less than 5,200 square feet in area (Parcel C). |
Parcel #:
2630142015
2630142031
3
(Project Planner: Robert Williams)
Z050309
File Number:
Site Address:
2300 EVERGREEN ST (D2, Area 4)
Location:
2300 Evergreen Street (D2, Area 4)
Owner:
RAYGOZA ELOY/NORMA, 1704 KERRY LN, SANTA ROSA, CA, , 95403
Applicant:
NORMA & ELOY RAYGOZA, 1704 KERRY LANE, SANTA ROSA, CA, , 95403
Proposal:
| The applicant is proposing to replace a deteriorated single family residence with a new single family residence. |
| Since the zone is Light Industrial, use of the property for residential purposes is not in conformance with current |
| land use regulations. Therefore the proposed project is required to obtain the following entitlement from the |
| Zoning Administrator: |
|
| ZONING ADMINISTRATOR'S SPECIAL PERMIT to reconstruct a nonconforming residential use, (a 1,000± |
| square foot home and 400± square foot detached garage) on 0.16± developed acres in the Light Industrial (M-1) |
| zone. |
|
| (Concurrent with DR06-021, North Sacramento Design Review). |
|
Parcel #:
2770081004
4
(Project Planner: Lindsey Alagozian)
Z050218
File Number:
Site Address:
4465 H ST (D3, Area 1)
Location:
4465 H STREET (D3, Area 1)
Owner:
AMERICAN LUTHERAN CHURCH OF THE CROSS OF, 4465 H ST, SACRAMENTO, CA, , 95819
Applicant:
ED MAJICA, AIA, MOJICA ARCHITECTURE STUDIO, 2588 ROGUE WAY, ROSEVILLE CA, 95747
Proposal:
| The applicant is requesting to demolish an existing single family residence used as a parish house for an |
| existing church facility and construct a 1,350 square foot replacement residence. The site was approved with a |
| Special Permit; therefore, any modification to the site requires a Modification. This project requires a Special |
| Permit Major Modification at the Zoning Administrator level: |
|
| Zoning Administrator Special Permit Major Modification to demolish an existing residence and construct a 1,350 |
| square foot residence to be used as a parish house for the church facility 0.34 developed acres in the Standard |
| Single Family (R-1) zone. |
Parcel #:
0040302012
5
(Project Planner: Lindsey Alagozian)
Z050328
File Number:
Site Address:
205 24TH ST (D3, Area 4)
Location:
205 24TH ST (D3, Area 4)
Owner:
COURTYARD PRIVATE SCHOOL, 205 24TH ST, SACRAMENTO, CA, , 95816
Applicant:
LIONAKIS BEAUMONT DESGIN GROUP, 1919 19TH STREET, SACRAMENTO, CA, , 95814
Proposal:
| Request is to construct the Courtyard Private School in phases. Phases 1-3 are complete. Phase 4 is to |
| complete interior improvements to Multi-Purspose Room. Phase 5 is the construction of alley improvements. |
| Phase 6 is the construction of the access road from 25th Street and Phase 7 is for the kindergarten classroom |
| and play yard improvements. The Courtyard Private School project was approved with a Special Permit. |
| Therefore, the proposed project requires the following entitlement by the Zoning Administrator: |
|
| Special Permit Major Modification to change conditions of approval allowing the construction of the Courtyard |
| Private School in a total of seven phases. |
Parcel #:
0030091023