Swanston Station Transit Village Plan

The Swanston Station Transit Village Plan will prepare land use plans, traffic/infrastructure studies, environmental analysis, urban design plans, and financing/implementation strategies to implement transit-oriented development around the Swanston Light Rail Station in the City’s North Sacramento Community Plan Area. Additionally, the Swanston Station Transit Village Plan will provide land use, parking/circulation, open space and infrastructure goals, policies, and objectives, and implementation measures which will guide land use and development decisions around the station over the next twenty years.

Additional Swanston Information

 

Project Scope and Schedule

Scope

The Swanston Station Transit Village Plan will take an estimated two years to complete. The following work is planned for this project:

  • Land Use Plan
  • Urban Design Plan
  • Development and Financing Strategy
  • Environmental Analysis
  • Traffic Study
  • Infrastructure Analysis
  • Public Outreach

      Project Information

Public Involvement & Schedule

Meeting

Date

Presentations/Summaries

Community Newsletter #1

 

  

Community Workshop#1

5/13/06

Wkshp 1 Presentation
Wkshp 1 Summary

Community Newsletter #2

   

Community Workshop #2

10/18/06

Wkshp 2 Presentation
Wkshp 2 Summary

Community Workshop #3

4/16/2007

Wkshp 3 Presentation

Planning Commission

Late Fall/Early Winter 2007

 

City Council

Summer 2007

 


Resources

 

Contact Information

Fedolia "Sparky" Harris, Senior Planner
Transportation Planning, Department of Transportation
New City Hall
915 I Street, 2nd Floor , Sacramento, CA 95814
(916) 808-2996

 

Page last modified at