spacer 700/800 Block and 10th& K Street Update
spacer

What's New?

Notice of Preparation of Draft Environmental Impact Report (DEIR) for the 1012 K Street Project

Please click here to view the DEIR.

 

K STREET STREETSCAPE RFP (PDF) 5-18-07

The following are supporting documents for the K Street Streetscape RFP:

Click here for Subconsultant Utilization Form.

700/800 K Street ERN (PDF) Oct. 14, 2005

10th and K Street and 700/800 Block Developer Recommendations Update

JKL Corridor Update: K Street Proposals meeting, June 13, 2005

9th and L Streets Parking Structure Feasibility Study Update Apr. 29, 2005

T
he 9th and L Streets Parking Structure Feasibility Study is complete. This final version adds additional cost factors for architectural enhancement and the extra increment of cost necessary to create a retail shell along L Street. These additional costs make the structure even less feasible than the assumptions in the previous study. In summary the study concludes that the structure is not currently financially feasible and a substantial amount of new development nearby that had no other parking would be required to close the financial gap. It should be recognized that some of this analysis is based on future development assumptions that are highly speculative.

The study utilized a 358-space garage on a portion of the half block as the preferred alternative based on the current magnitude of demand. The Central City Parking Master Plan that is underway is intended to provide information and analysis that will help determine what locations have the greatest need for new public parking facilities in the Central City. That study is expected to be completed before the end of the year.

CITY RESPONSE TO 700/800 BLOCK PROPERTY OWNERS

Information on the 10th/K RFP Pre-Submittal Meeting held on March 3, 2005.

J-K-L Charrette

In response to increased development interest and the proposed Downtown Redevelopment Plan Amendment, the City's Economic Development Department in conjunction with the Mayor's Office and DSP hosted the J-K-L Corridor Workshop in an effort to receive community input on a new vision for the area. A two-part process was created for receiving input:

BACK TO TOP

  1. The initial J-K-L Corridor Workshop, which was held on October 23, 2004 on the ground floor of the Renaissance Tower at 8th and K streets; and
  2. A follow-up public meeting on December 1, 2004, to review and provide feedback on the results of the workshop.