Upcoming Projects
- South Land Park Phase 2
JuneDecember 2007
- South Land Park Area: Normandy Lane to the South, Ridgeway Drive to the north, Euclid Avenue to the west and Crestwood way to the east.
- This project will include back yard main relocation, replacement of undersized and deteriorated steel water mains, upgrading of fire hydrants and water meter installation. For more information on this project, contact Brett Ewart at (916) 808-5454.
- Bowman and Wisconsin
June 11September 28, 2007
- Bowman and Wisconsin from Northgate to Natoma.
- This project will include replacement of undersized and deteriorated steel water mains, upgrading of fire hydrants and water meter installation. For more information on this project, contact Stu Wiliams (916) 808-5454.
- Downtown Sacramento Phase 1
May 21, 2007Beginning September
- Downtown Area: F Street to the south, B Street to the north, 7th Street to the west and 21st Street to the east.
- This water meter project will place meters in alleys at commercial and residential properties. Work will include excavation, backfill, surface restoration and meter installation. For more information, contact Chris Powell at (916) 808-5454.
- Downtown Sacramento Phase 2
Mid JulyNovember 2007
- Downtown Area: R Street to the south, F Street to the north, 7th Street to the west and 21st Street to the east.
- This water meter project will place meters in alleys at commercial and residential properties. Work will include excavation, backfill, surface restoration and meter installation. For more information, contact Chris Powell at (916) 808-5454.
- Capitol/L Alley Sewer Replacement
September 1November 2007
- Capitol/L Alley from 18th Street to 19th Street.
- This project will replace the combined system main, service laterals, manholes, substandard drain inlets and drain leads. Work will include retrofitting all unmetered commercial and residential properties with a meter. For more information, contact Dale Mathison at (916) 808-5454.
*All project boundaries are approximate.
|