ROSEVILLE ROAD BRIDGE REPLACEMENT PROJECT OVER ARCADE CREEK

Underneath Roseville Road Bridge, graffiti on pillars
Figure 1- November 2013: Existing Condition

Project Description

The project, located approximately one half mile north of the intersection of Connie Way and Roseville road, replaced the existing Roseville Road Bridge over Arcade Creek.

Roseville Road Bridge Replacement Over Arcade Creek

Figure 2 - December 2016: New Bridge

Benefits

The new bridge improved safety for pedestrians and bicyclists by providing wider bike lanes and sidewalks. The project also improved the hydraulics of Arcade Creek.

Costs and Funding

Total project cost was<$7 million. The project was funded through the Highway Bridge Program and local transportation funds.

Schedule

Construction was completed in January of 2016.

Contact

Matthew Johns, Project Manager
Office: (916) 808-5760
Email: mjohns@cityofsacramento.org